Home
Education
Truman College Construction Update
Education
Truman College Construction Update | Truman College Construction Update |
| 03/27/2009 | |
|
Crews have installed 27 of the 90 caissons that will support the new Larry McKeon Administrative Building, working at the rate of three or four a day. If all goes well, they should finish by the first or second week of May. The last of the "spoils," soil removed after grading, have been removed. Construction traffic will continue to use the entrance on Wilson.
Please call or email with questions or concerns.
Clifton Truman Daniel
|