Hazel Water Main Construction Update
03/27/2009

ImageVia the Department of Water Management

Crews from the Department of Water Management are finishing up the sewer installation as we speak. Currently, they're working at Hazel and Montrose and will be done with that leg by Monday.

After the sewer installation is finished, they will turn around and move north, installing catch basins on Hazel at Sunnyside and Agatite. Once the catch basins are done, they'll move out of the area. Work is expected to be finished by Monday, April 6th.