Marine Drive Resurfacing Update - November 2
11/02/2009

The bus pads on the east side of Marine Drive will be completed today.  These areas need to remain closed to traffic/ parked vehicles for 3-7 days.  In the interim, a small crew will be on site saw-cutting the pavement in preparation for utility structure adjustments and the bus pads on the west side of Marine.  Removal of the west side bus pads will be done after the pads on the east side are open.

The curb & gutter in front of Walt Disney School will also be rehabilitated. There are no classes on Friday, November 6th, so the contractor will remove and replace the curb in front of the school then.

Questions?  Call Alderman Shiller's 46th Ward Community Service Office at 773 878 4646.